RE: Recharter - Last Chance



 
adrian

> ---
> NEW
>   Oct 2007    First version WG I-Ds for GMPLS source-controlled and 
> explicitly-routed Ethernet networks
> ---
> NEW
>   May 2008    Submit protocol extensions for GMPLS 
> source-controlled and 
> explicitly-routed Ethernet networks for IESG review
> 
> ====

is that actually realistic ? knowing that work at IEEE 
started on March 2007 and expected to take a couple of
cycles ?

from the PAR 
<http://standards.ieee.org/board/nes/projects/802-1Qay.pdf>

Expected Date of Submission for Initial Sponsor Ballot: 
August 2010 Projected Completion Date for Submittal to 
RevCom: February 2011

hence, assuming this work that started in March 2007 may
be stabilized by mid-2008 - how to achieve that milestone?
should it not be something like Dec. 2008.

in case the work items are expected to be achieved in a
presence of multiple steps like initially considered i 
would suggest then start working on functional specs &
specific specs that could be delivered once the IEEE 
spec. further stabilizes.

just tyring to prevent yet another milestone change in a
couple of months

-d. 


> -----Original Message-----
> From: owner-ccamp@ops.ietf.org 
> [mailto:owner-ccamp@ops.ietf.org] On Behalf Of Adrian Farrel
> Sent: Thursday, August 16, 2007 11:11 AM
> To: ccamp@ops.ietf.org
> Subject: Recharter - Last Chance
> 
> Hi,
> 
> Following from the small comments received on the list, here 
> is the modified 
> charter update proposal.
> 
> This is your last chance to comment before we send it to the IESG for 
> approval.
> 
> Adrian and Deborah
> 
> ===
> 
> First paragraph
> 
> OLD
> The CCAMP working group coordinates the work within the IETF defining
> a common control plane and a separate common measurement plane for
> physical path and core tunneling technologies of Internet and telecom
> service providers (ISPs and SPs), e.g. O-O and O-E-O optical switches,
> ATM and Frame Relay switches, MPLS, GRE, in cooperation with the MPLS
> WG.
> 
> NEW
> The CCAMP working group coordinates the work within the IETF defining
> a common control plane and a separate common measurement plane for
> physical path and core tunneling technologies of Internet and telecom
> service providers (ISPs and SPs), e.g. O-O and O-E-O optical switches,
> TDM switches, Ethernet switches, ATM and Frame Relay switches, and
> MPLS and GRE in cooperation with the MPLS WG.
> 
> ===
> 
> New paragraph in the list of Scope bullets.
> Suggest to place it after:
> "- Definition of MIB modules and other OAM techniques relevant to the
>    protocols and extensions specified within the WG."
> and before:
> "CCAMP WG currently works on the following tasks:"
> 
> - Work on GMPLS procedures and extensions to support source-
>   controlled and explicitly-routed Ethernet data paths for
>   Ethernet data planes that are already approved by an SDO with
>   responsibility for the Ethernet data plane. It is expected that
>   the primary SDO in this case is the IEEE. Note that the
>   specification or modification of Ethernet data planes is out of
>   scope.
> 
> ===
> 
> Final paragraph
> 
> OLD
> In doing this work, the WG will work closely with at least the
> following other WGs: MPLS, ISIS, OSPF, IDR, L1VPN and PCE. The WG
> will also cooperate with the ITU-T.
> 
> NEW
> In doing this work, the WG will work closely with at least the
> following other WGs: MPLS, ISIS, OSPF, IDR, L1VPN, and PCE. The
> WG will also cooperate with the ITU-T and the IEEE 802.1.
> 
> ===
> 
> Milestone revisions (see below for full revised milestone list)
> 
> OLD
>   Jan 2006    First version WG I-D for Protocol solutions for MLN/MRN
> NEW
>   Sep 2007    First version WG I-D for Protocol solutions for MLN/MRN
> ---
> OLD
>   Mar 2006    First version WG I-D GMPLS OAM Requirements
> NEW
>   Sep 2007    First version WG I-D GMPLS OAM Requirements
> ---
> OLD
>   Apr 2006    First version of WG I-D for additional MIB 
> module to cover 
> RSVP-TE signaling extensions
> NEW
>   Nov 2007    First version of WG I-D for additional MIB 
> module to cover 
> RSVP-TE signaling extensions
> ---
> OLD
>   Jun 2006    Submit Informational I-D for Analysis of 
> inter-domain issues 
> for disjoint and protected paths for IESG review
> NEW
>   Oct 2007    Submit Informational I-D for Analysis of 
> inter-domain issues 
> for disjoint and protected paths for IESG review
> ---
> OLD
>   Oct 2006    Submit MPLS to GMPLS migration strategies I-D 
> for IESG review
> NEW
>   Sep 2007    Submit MPLS-TE to GMPLS migration strategies 
> I-D for IESG 
> review
> ---
> OLD
>   Nov 2006    Submit ASON Routing solutions I-D for IESG review
> NEW
>   Jan 2008    Submit ASON Routing solutions I-D for IESG review
> ---
> OLD
>   Dec 2006    Submit Requirements for Multi-Layer and 
> Multi-Region Networks 
> I-D for IESG review
> NEW
>   Oct 2007    Submit Requirements for Multi-Layer and 
> Multi-Region Networks 
> I-D for IESG review
> ---
> OLD
>   Jan 2007    Submit MPLS-GMPLS interworking requirements and 
> solutions I-D 
> for IESG review
> NEW
>   Sep 2007    Submit MPLS-TE/GMPLS interworking requirements 
> I-D for IESG 
> review
> ---
> OLD
>   Feb 2007    Submit Evaluation of existing protocols for 
> MLN/MRN for IESG 
> review
> NEW
>   Oct 2007    Submit Evaluation of existing protocols for 
> MLN/MRN for IESG 
> review
> ---
> OLD
>   Mar 2007    Submit OSPF-TE/GMPLS MIB module for MIB doctor 
> and IESG review
> NEW
>   Dec 2007    Submit OSPF-TE/GMPLS MIB module for MIB doctor 
> and IESG review
> ---
> OLD
>   Jun 2007    Submit GMPLS OAM Requirements I-D for IESG review
> NEW
>   Feb 2008    Submit GMPLS OAM Requirements I-D for IESG review
> ---
> OLD
>   Aug 2007    Submit Protocol solutions for MLN/MRN I-D for 
> IESG review
> NEW
>   Mar 2008    Submit Protocol solutions for MLN/MRN I-D for 
> IESG review
> ---
> OLD
>   Dec 2007    Submit MIB module for RSVP-TE signaling 
> extensions for MIB 
> doctor and IESG review
> NEW
>   Apr 2008    Submit MIB module for RSVP-TE signaling 
> extensions for MIB 
> doctor and IESG review
> ---
> OLD
>   Dec 2007    Recharter or close Working Group
> NEW
>   Dec 2008    Recharter or close Working Group
> ---
> NEW
>   Oct 2007    First version WG I-Ds for GMPLS source-controlled and 
> explicitly-routed Ethernet networks
> ---
> NEW
>   May 2008    Submit protocol extensions for GMPLS 
> source-controlled and 
> explicitly-routed Ethernet networks for IESG review
> 
> ====
> 
> Goals and Milestones (full revised milestone list)
> 
> Done    Post strawman WG goals and charter
> Done    Identify and document a limited set of candidate 
> solutions for 
> signalling and for measurement. Among candidate control 
> solutions to be 
> considered are the existing GMPLS drafts.
> Done    Build appropriate design teams
> Done    Submit WG document defining path setup portions of 
> common control 
> plane protocol
> Done    Submit WG document defining common measurement plane protocol
> Done    Submit LMP MIB to IESG
> Done    Submit protection & restoration documents to IESG
> Done    Submit ASON signaling requirements doc to IESG
> Done    Submit GMPLS MIBs to IESG
> Done    Produce CCAMP WG document for generic tunnel tracing protocol
> Done    Produce CCAMP WG document for multi-area/AS signaling 
> and routing
> Done    Submit ASON routing requirements doc to IESG
> Done    Submit revised charter and milestones to IESG for 
> IESG consideration 
> of more detailed deliverables and determination of usefulness of 
> continuation of WG
> Done    First version WG I-D for Advertising TE Node 
> Capabilities in ISIS 
> and OSPF
> Done    First version WG I-D for Automatic discovery of MPLS-TE mesh 
> membership
> Done    Submit ASON Routing evaluation I-D for IESG review
> Done    Cross-WG review of I-D for Advertising TE Node 
> Capabilities in ISIS 
> and OSPF
> Done    First version WG I-D MPLS to GMPLS migration strategies
> Done    First version WG I-D Requirements for Multi-Layer and 
> Multi-Region 
> Networks
> Done    First version WG I-D for Evaluation of existing protocols for 
> MLN/MRN
> Done    First version of WG I-D for ASON Routing solutions
> Done    Submit RSVP-TE extensions for inter-domain signaling 
> I-D for IESG 
> review
> Done    Submit Per-domain path computation signaling I-D for 
> IESG review
> Done    First version of WG I-D for OSPF-TE/GMPLS MIB module
> Done    Submit GMPLS signaling in support of Call Management 
> I-D for IESG 
> review
> Done    First version WG Informational I-D for Analysis of 
> inter-domain 
> issues for disjoint and protected paths
> Done    Submit I-D for Advertising TE Node Capabilities in 
> ISIS and OSPF for 
> IESG review
> Done    Submit GMPLS/ASON lexicography I-D for IESG review
> Done    First version WG I-D MPLS-GMPLS interworking requirements and 
> solutions
> Done    Submit LSP Stitching I-D for IESG review
> Done    Submit I-D for Automatic discovery of MPLS-TE mesh 
> membership for 
> IESG review
> Done    Submit GMPLS routing and signaling interoperability 
> advice I-D for 
> IESG review
> Sep 2007    First version WG I-D for Protocol solutions for MLN/MRN
> Sep 2007    First version WG I-D GMPLS OAM Requirements
> Sep 2007    Submit MPLS-TE to GMPLS migration strategies I-D 
> for IESG review
> Sep 2007    Submit MPLS-TE/GMPLS interworking requirements 
> I-D for IESG 
> review
> Oct 2007    First version WG I-Ds for GMPLS source-controlled and 
> explicitly-routed Ethernet networks
> Oct 2007    Submit Informational I-D for Analysis of 
> inter-domain issues for 
> disjoint and protected paths for IESG review
> Oct 2007    Submit Requirements for Multi-Layer and 
> Multi-Region Networks 
> I-D for IESG review
> Oct 2007    Submit Evaluation of existing protocols for 
> MLN/MRN for IESG 
> review
> Nov 2007    First version of WG I-D for additional MIB module 
> to cover 
> RSVP-TE signaling extensions
> Dec 2007    Submit OSPF-TE/GMPLS MIB module for MIB doctor 
> and IESG review
> Jan 2008    Submit ASON Routing solutions I-D for IESG review
> Feb 2008    Submit GMPLS OAM Requirements I-D for IESG review
> Mar 2008    Submit Protocol solutions for MLN/MRN I-D for IESG review
> Apr 2008    Submit MIB module for RSVP-TE signaling 
> extensions for MIB 
> doctor and IESG review
> May 2008    Submit protocol extensions for GMPLS 
> source-controlled and 
> explicitly-routed Ethernet networks for IESG review
> Dec 2008    Recharter or close Working Group
> 
> 
> ====
> Thanks,
> Adrian
> 
> 
> 
>